Apr 30, 2024 | Construction

April 2024 Construction Update You may have noticed a lot of action in the lap pool construction area! Here’s a quick recap of what has been going on:

  • The underground utility work is officially complete!
  • The kiddie pool, community pool, and hot pool forms are nearly complete, and the plumbing for all three pools is finished.
  • Rebar installation is nearly complete on the kiddie pool and community pool, and installation on the hot pool is soon to follow.
  • Next up, the crew will begin concrete work on the kiddie pool, community pool, and hot pool.