Construction

May 2024 Construction Update

May 2024 Construction Update

Our construction team continues to make strides on the lap pool reconstruction project! The pool forms, plumbing, and rebar on the kiddie splash pad area, hot pool, and community are complete. Last week, we passed all the necessary testing and poured the concrete...

April 2024 Construction Update

April 2024 Construction Update

You may have noticed a lot of action in the lap pool construction area! Here's a quick recap of what has been going on: The underground utility work is officially complete! The kiddie pool, community pool, and hot pool forms are nearly complete, and the plumbing for...

Updated Timeline for Capital Campaign Project

Updated Timeline for Capital Campaign Project

We started construction on the final phase of our Capital Campaign in September of 2023 with the plan to replace the aging lap pool with a new community pool, lap pool, hot pool, and kiddie splash pad area. We are disappointed to share that our timeline has been...

OTHS Breaks Ground on Lap Pool Reconstruction Project

OTHS Breaks Ground on Lap Pool Reconstruction Project

With summer drawing to a close and the new pump house project nearing completion, we are ready to break ground on the long-anticipated renovation of the lap pool, shallow pool and kiddie splash pad area. Although the existing hot pools will remain open during...

Construction Update & Pool Maintenance Week

Construction Update & Pool Maintenance Week

Our pool reconstruction project start date is getting closer. At this time, all of our pools will stay open through mid September as our building permits are still with the city of Steamboat Springs. We will let you know the lap pool area closure date as soon as we...

Pump House Construction Update

Pump House Construction Update

Construction on our new Pump House started at the end of 2022 and has been full steam ahead ever since! A heavy snow year created some challenges when it came to shoring up the hillside in preparation for the construction of the pump house, but our amazing HLCC team...

Groundbreaking Ceremony on December 14th

Groundbreaking Ceremony on December 14th

December 14th at 1:30pm. Please RSVP to join us as we celebrate the start of construction of the new Old Town Hot Springs Pump House! The groundbreaking ceremony is located at the Old Fish Creek Falls Rd. Parking Lot. Refreshments will be in the Community Room after...

Old Fish Creek Falls Rd. Parking Lot Closed for Construction

Old Fish Creek Falls Rd. Parking Lot Closed for Construction

Exciting news! Our foundation building permit was approved by the City of Steamboat Springs, which means construction can begin on the new Pump House. Starting Thursday, December 1, the Old Fish Creek Falls Rd. parking lot will be closed, and fencing will go up....

Old Town Hot Springs Hires Wember Inc.

Old Town Hot Springs Hires Wember Inc.

On June 1, Old Town Hot Springs officially hired Wember Inc. as the owner’s representative in the management of our Capital Campaign Project. Wember has represented owners in the project management of capital improvement projects since 2004. Their committed staff...